Mold Process Production Schedule
2008.05.12
Q. Our company is performing plastic molding. There are 10 to 20 molding machines and we have several hundred types of mold. When making our production schedule, it's essential that we decide whether a mold is usable or not. If we can't, then we can't make a schedule that is executable on the factory floor. However, because there are an extremely large number of mold types, we have the additional restriction that some molds made be in repair and so unavailable for use. Please, tell us a way of creating a production schedule that considers molds.
Make use of production scheduling software simulations to the greatest extent
A. Bottlenecks with production schedules are not just with the main resources such as mold machines and press machines, but also with the sub-resources such as molds, jigs and workers and this is what makes production scheduling difficult.
In particular, it is often the case that there is only one mold for each item so that the production schedule has the restriction that the same item mold cannot be used in 2 or more places at the same time. Generally, for each item there are no mold units available or several types of mold (sub-resources) are necessary at the same time. Because of this, as the restriction conditions to the production schedule become more and more complex, it becomes increasingly difficult for a person to consider about all these in their head.
However, it is possible to set all the above restriction conditions in a production scheduler and simulate them.
First of all, set the molding process to use a mold (Scheduler Diagram 1)、
![]() |
then set up the orders (Scheduler Diagram 2).
![]() |
Next, simulate with the production scheduler and the result is like Scheduler Diagram 3.
![]() |
If we take a look at the production scheduler's results, we can see that even if the molding machine is free, but the mold is not available, then production cannot be done. After that, if we increase the data set up, then we get a production schedule result close to an actual operating situation.
From here, being able to overcome the problem of trying to add new production methods just by changing the set up is one of the benefits of simulating with a production schedule software.
With regard to your company's dilemma, I think that the key to solving your problem is to use a production scheduler and try to actually simulate the situation with real data.